Delivery Timeline & Milestones

Project Timeline Summary (6 Weeks)

Phased delivery plan with weekly checkpoints and acceptance gates

Phase Duration Focus Acceptance Criteria
Phase 1: Foundation Week 1 Project setup, environments, waitlist site, admin/mobile kickoff Repos, CI pipeline, environments provisioned; waitlist page live; admin/mobile shells ready
Phase 2: Core Backend Weeks 2-3 Auth, user profiles, task and reward engines; admin dashboard baseline; mobile layout scaffolding APIs implemented with tests and documented contracts
Phase 3: Client Experience Weeks 4-5 Mobile/web UI flows, playback tracking, cashout UX User journeys verified end-to-end on staging
Phase 4: Launch Readiness Week 6 Hardening, UAT, app store assets, rollout plan UAT sign-off, release builds prepared, go-live checklist closed

Week-by-Week Delivery Plan

Detailed weekly activities, owners, and acceptance checkpoints

Week Focus Key Deliverables Acceptance Criteria
Week 1 Foundation, Waitlist & Layout Kickoff Repo setup, CI/CD, env config, database schema draft; launch marketing homepage with waitlist capture; admin dashboard shell and mobile app initial layout Pipelines green, staging accessible, schema reviewed; waitlist captures leads; admin/mobile shells demoed
Week 2 Core APIs I + Parallel UI Foundations Auth, invite codes, user profiles, admin roles; admin dashboard baseline screens; mobile layouts for onboarding and tasks; waitlist wired to backend storage Postman/Swagger documented, unit tests passing; waitlist submissions persisted; admin/mobile screens clickable on staging
Week 3 Core APIs II Tasks, playback tracking, rewards, cashout logic Endpoints covered by integration tests on staging
Week 4 Client UX I Core user journeys: onboarding, tasks, wallet, rewards Staging walkthrough recorded; no critical UI bugs
Week 5 Client UX II Playback tracking UI, cashout flow, notifications, polish Device/browser matrix tested; accessibility pass completed
Week 6 Launch Readiness UAT fixes, performance tuning, store assets, release builds UAT sign-off, go-live checklist completed, release tagged

Milestones & Acceptance Gates

Clear checkpoints required for progression and payment release

Milestone Due Acceptance Criteria Evidence
Foundation Complete End of Week 1 CI/CD live, staging URL, schemas reviewed and approved; waitlist page live capturing leads; admin/mobile shells reviewed CI runs, staging demo, schema doc
Core Backend Ready End of Week 3 Auth, tasks, rewards, cashout APIs with tests Swagger links, test reports, staging walkthrough
Client Journeys Ready End of Week 5 Onboarding-to-cashout flow verified on staging Recorded demo, test checklist, bug list triaged
Launch-Ready Release End of Week 6 UAT sign-off, release builds, store assets approved UAT report, release notes, app store artifacts

QA, Security & Launch Readiness

Quality, performance, and compliance checks leading to go-live

Area Activities Acceptance
Testing & Quality Unit, integration, UAT cycles; regression before release Test coverage reports and UAT sign-off
Security Auth hardening, rate limiting, dependency checks No critical vulnerabilities; SAST/DAST reports clean
Performance API latency baselines, client performance, load sanity Meets agreed SLAs on staging benchmarks
Release Release notes, rollback plan, monitoring and alerting ready Go-live checklist completed and approved

Dependencies & Assumptions

Items required to keep the 6-week schedule on track

Stakeholder availability for weekly reviews and UAT sign-offs.

App store accounts (Google Play, Apple Developer) provisioned by Week 5 for submission prep.

Third-party keys (Paystack, email) available before Week 3 for integration testing.

Content and branding assets ready by Week 4 for client/UI polishing and store listings.

Decision turnaround for change requests within 48 hours to avoid schedule impact.